Music Business

Music Modernization Act A ‘Countdown to Modernity’ – Progress Chart For Mechanical Licensing Collective

1In this piece, the people at Music Technology Policy provide a chart listing the key events in the necessary path to launch in order for the Mechanical Licensing Collective as needed by the recently ratified Music Modernization Act.

_________________________

Guest post by Editor Charlie of Music Technology Policy

As best we can tell from the outside looking in, this chart has the dates for key events in the critical path to launch for the Mechanical Licensing Collective as required by the Music Modernization Act–the “Countdown to Modernity.”

4This chart is a work in progress, and if anyone sees anything wrong in it or something that should be clarified or corrected, please let us know.  It should be considered a draft, but we hope that it will solidify over the next few weeks.

To our knowledge, no one else has published a chart like this.  The main takeaway from this chart should be the clock is ticking and time is going by.  Our prediction?  Time will become the MLC’s biggest enemy, if that hasn’t already happened in the drafting of the Music Modernization Act.  What we don’t see in the MMA is any discussion of what happens if a deadline is blown for whatever reason.

But mark your calendars–we see the first key date as January 7, 2019.  That’s 64 days from now and holidays count.

ARTIST RIGHTS WATCH
COUNTDOWN TO MECHANICAL LICENSING COLLECTIVE LAUNCH
WEEK 4

KEY DATES SCHEDULE FROM ENACTMENT DATE (10/11/18)

TO LICENSE AVAILABILITY DATE (1/1/21)

EVENTACCCOMPLISHEDWHO OWNS?TIME EXPIRED   BEFORE LADTIME REMAINING TO LAD
REQUEST FILING TO BE MLCSTATUS UNKNOWN—Deadline  1/7/2019COPYRIGHT OFFICE90 DAYS726 days
DESIGNATION OF MLCSTATUS UNKNOWN—Deadline  7/7/2019COPYRIGHT OFFICE270 days545 days
FORMATION OF MLC NONPROFITSTATUS UNKNOWNMLC4 weeks112 weeks and 5 days
SUBSTITUTION OF BLANKET LICENSE FOR ALL EXISTING COMPULSORY LICENSESAUTOMATIC 1/1/2021COPYRIGHT OFFICE 789 days
MLC BUDGETSTATUS UNKNOWN

(Assume deadline of 1/7/19)

MLC/DLC/CRJ 112 weeks and 5 days
INITIATE ASSESSMENT PROCEEDING w/CRJs[MUST COMMENCE NO LATER THAN 7/7/2019]

STATUS UNKNOWN

MLC/DLC/CRJ271 days545 days
ASSESSMENT RULING[PUBLISHED IN FR NO LATER THAN 7/7/2020]MLC/DLC/CRJ637 days179 days
APPEAL OF ASSESSMENT RULING30 DAYS AFTER PUBLICATION OF ASSESSMENT RULINGMLC/DLC/CRJ/ DCCOA667 days149 days
MLC BUSINESS PLANSTATUS UNKNOWN

(Assume deadline of 1/7/19)

MLC/CO90 DAYS726 days
ANNOUNCED BOARD NOMINEESSTATUS UNKNOWN

Update on Nominations (Deadline November 15, 2018):  NMPAand NSAI are accepting nominations for board seats.  Songwriter board selection by Steve Bogard (NSAI), Rick Carnes (SGA), Lynn Gillespie Chater (SGA), Dallas Davidson (BMI), Chris DeStefano (NSAI), Bob DiPiero (BMI), Dan Foliart (ASCAP), Adam Gorgoni (SONA), Michele Lewis (SONA), Paul Williams (ASCAP)

(Assume deadline of 1/7/19)

MLC90 DAYS726 days
APPOINTED BOARDSTATUS UNKNOWN

(Assume deadline of 1/7/19)

MLC/CO90 DAYS726 days
APPOINTED DLCSTATUS UNKNOWN—Deadline  7/7/2019COPYRIGHT OFFICE270 days545 days
ENGAGED  MLC VENDORSSTATUS UNKNOWN

(Assume deadline of 1/7/19)

MLC90 DAYS726 days
PAID MLC VENDORSSTATUS UNKNOWN (ASSUME 7/7/2020 IF NO APPEAL OF ASSESSMENT)MLC270 days545 days
ANNOUNCE MLC DATA STANDARDSSTATUS UNKNOWNMLC/DLC  
REGULATIONS*STATUS UNKNOWNCOPYRIGHT OFFICE  
COMMENTS AND REPLY COMMENTS ON REGULATIONSSTATUS UNKNOWNALL  
EXPLANATION OF OPERATIONS: HOW TO REGISTER WITH MLC AND COST OF REGISTRATIONSTATUS UNKNOWN

(Assume deadline of 1/7/19)

MLC/CO90 DAYS726 days
REGISTRATION START DATESTATUS UNKNOWN   

MLC=Mechanical Licensing Collective

DLC=Digital Licensee Coordinator

CRJ=Copyright Royalty Judges

DCCOA=District of Columbia Circuit Court of Appeals

CO=Copyright Office

LAD=License Availability Date

*Topic areas to be updated as announced

Share on: